The Illinois company saved significant man-hours by planning ahead.
A large manufacturing company in Harvey, Illinois, needed 170 feet of R-12 Thermaduct with dimensions of 148 inches by 60 inches. Sheet Metal Werks had to lift and install the pieces onto a rooftop feeding two air units.
In this industry, we all know that time is money. Finding ways to think outside the box and reduce man-hours is the key to profitability — and happy clients. Sheet Metal Werks, a full-service fabricator in Arlington Heights, Illinois, recently demonstrated how pre-planning can make a world of difference.
The scope of the project consisted of approximately 170 feet of R-12 Thermaduct with dimensions of 148 inches by 60 inches. The Thermaduct was to be lifted and installed onto a rooftop feeding two make-up air units that would supply a large manufacturing company in Harvey, Illinois.
Given the size of this ductwork, this accomplishment was no small feat. But superintendent John Crne says that it all came back to doing more planning in the shop — as opposed to in the field where you’re working on a rooftop and out in the elements.
Logistically getting the material to the site initially led the company toward stacking it on flatbed trucks to save on shipping. But had the company stopped the thought process there, they would never have seen the tremendous back-end efficiency.
“We realized that if we put more coordination and planning into assembling ductwork and sending it in larger sections that the contractor would pay more upfront but really save on the back end,” Crne says. “Whenever you can coordinate and do more planning in the shop — where you’re working in a controlled environment — that’s a win.”
According to Crne, had they shipped ductwork to the site as initially planned, it would have required 29 crane picks—which they brought down to 12. Had they lifted individually, they would have had 27 connections to complete on the roof—which was brought down to only 10.
“Reducing the work in the field made this project turnkey,” continues Crne. “We did all the supports, the connections, and weatherproof covers. And we were able to eliminate the insulation subcontractor coming out after the installation. That three-hour window was from the time we hoisted the first section to the completion.”
Crne says that the lightweight material allowed them to land each section on a roof rail and then push and connect as they moved down the line. It was as streamlined as a project can get. The total weight of the Thermaduct was only 1,900 pounds versus 5,400 pounds if it were to be done in Galvanized metal.
“We really put a lot of emphasis on upfront coordination and planning with the customer,” Crne says. “We’re looking at how we can save the end user time and money, as well as make them more profitable. When the contractor is more profitable, so are we.”
In this case, the installing contractor was Midwest Mechanical — a company that Sheet Metal Werks has partnered with for decades. A good working relationship with the contractor is always critical, adds Crne.
“I would say that the spooling of the material was a key to the success of this project,” Crne says. “The Thermaduct had built-in lifting lugs, fully sealed connections, as well as all the struts and supports that would usually be installed in the field. Because it was so lightweight, they slid onto the rails easily and then it was a drop-and-go situation. There was no circling back. We finished each section as we went, which really streamlined the entire process.”
This was also a result of forethought and planning, with the spacing of the roof rails kept just right to keep things moving.
“It all comes back to the fact that we were focused on taking away field labor hours wherever we could,” Crne says. “By moving those field labor hours into the shop, it’s always more productive and efficient. Had we not planned, and the roof rails were not spaced in a way that helped pull the connections, we would have added time back into the field.”
Crne says that the best lesson to come out of this project is that pre-planning and coordination are worth the effort. Any time you can add upfront cost to save on the back end of a project is always going to be more profitable for the contractor.
“I have been with Sheet Metal Werks for over 20 years and have witnessed firsthand how much our industry has changed,” he sums up. “This Thermaduct project was a great example of how we can truly shift those field hours into the shop. This is something we take great pride in, which ultimately makes our contractors more competitive, as well as continuing to help streamline project completion.”
Published: May 16, 2023
IN THIS ISSUE
Intech helps install sheet metal shade structures at California schools.
Zahner talks about how the Life Cycle Assessment accounts for the environmental impact of metal material from its initial extraction through manufacture and use and on to the end of its designed useful life.
Metals are different from nearly all other materials used in our built environment. Once the useful life has ended, the metal is collected and recycled.
Bulletproofing your business against a cyberattack can help protect you from today’s threats.
JPMorgan Chase & Co.’s global headquarters becomes AABCO’s next commercial HVAC client in NYC.
The Illinois company saved significant man-hours by planning ahead.
Sustainability is more than just an industry buzzword at Zahner. It's a daily commitment to preserving and protecting the natural resources we’ve been entrusted with and using them responsibly in the built environment.
With advertising, 128-year-old Welsch Heating & Cooling Co. isn’t afraid to try new ways to reach their customers — as long as they work.
SMACNA was asked to be part of a policy roundtable on supply chain for highly efficient heat pumps and related decarbonization technologies that are key parts of whole house retrofits.
The first quarter is always busy at SMACNA. We have lots of association events, our technical department is out in force, labor is starting its bargaining season and the government relations team is focused on many regulatory issues.
With the pandemic entering a new phase, construction has boomed with what are now widely known as “megaprojects.” Every day, it feels like there’s a new stadium, microprocessor factory or some other massive project getting underway. The demand for
In the last issue of SMACNews, I presented the first five of Grassi’s Top 10 Contractor Strategies for 2023. Those approaches to purchasing, procurement, prequalification, increased costs and project management are designed to cut through the noise
For contractors with collective bargaining agreements (CBAs) expiring in 2023, it is important to remember that most CBAs, including the Standard Form, include an “evergreen” or “automatic renewal” clause.