The contract between my client and its customer set a specific production schedule, and had incentives and penalties if certain deadlines were not met. My client’s customer was demanding completion on schedule, and threatening to enforce penalties.
Updated June 3, 2021
On September 13, 2001, a client contacted me regarding a project that had been disrupted by the tragic events of September 11. The contract between my client and its customer set a specific production schedule, and had incentives and penalties if certain deadlines were not met. My client’s customer was demanding completion on schedule, and threatening to enforce penalties.
Since one of my client’s key subcontractors was stuck in North Carolina during the shutdown of air travel, and was unable to return to Minnesota to complete the project on time, my client knew the first set of deadlines would be missed. Panicked, my client called and asked for help. Upon review of the contract, I realized that, fortunately, the following clause had been inserted in the contract:
Since the suspension of air travel was certainly a circumstance beyond anyone’s control, we were able to avoid the late penalties and set new deadlines. The project was completed with some delay; however, the client received all of its bonuses, and was able to maintain a good working relationship with the customer.
As this story demonstrates, in an increasingly uncertain world, force majeure clauses can make all of the difference.
Definitions
Black’s Law Dictionary defines “force majeure” as a clause “allocating the risk of loss if performance becomes impossible or impracticable, especially as a result of an event or effect that the parties could not have anticipated or controlled.” Similar clauses are also described as “act of God” or “unforeseen delay” clauses. The goal of all of these clauses is essentially the same — to protect a party when delays are imposed as a result of events outside of a party’s control.
When to Use These Clauses
When a contract contains either rewards or penalties for meeting deadlines, force majeure clauses are essential. Otherwise, the contractor will be held accountable for meeting a deadline, even if the delay is caused by forces outside its control.
Standard construction contracts deal with these unforeseen delays. For example, the Standard Agreement and General Conditions Between Owner and Constructor from ConsensusDocs addresses the issue directly:
ConsensusDocs 200 (2011 Ed., revised 2019); see also AIA Document A201-2017, Section 8.3.1. Whether it is a standard ConsensusDocs clause or a negotiated provision added to the contract, a contractor needs contractual provisions, which limit its responsibility for events outside its control, if an owner imposes deadlines.
Expanded Clause
While my client was able to successfully use the simple clause referenced above after the events of September 11, other clients have opted for the following more detailed, and comprehensive force majeure clause.
While this example may be “overkill,” it does demonstrate the extent to which some contractors are now seeking to avoid liability in the event of disruption beyond their control.
Must Be Outside Contractor’s Control
There are limits to force majeure clauses. A force majeure or act of God clause does not allow a contractor to avoid responsibility for any delay on a project. Indeed, courts have looked to whether the delays were truly the result of actions beyond the contractor’s control. See Unicover World Trade Corporation v. Tri-State Mint, 1994 WL 383244 (D.Wy. 1993). The acts of September 11 were obviously beyond anyone’s control. If the delay was reasonably foreseeable and within a contractor’s control, then the contractor will be unable to claim the protection of a force majeure clause, and be liable under the contract for delay.
Conclusion
In these troubled times, our government leaders have advised us to “prepare” for disruptions in our lives through purchasing duct tape, plastic, water and food. At the same time, we also should be vigilant in protecting our businesses. The presence of force majeure type clauses can be an invaluable tool in avoiding conflict and solving problems when business is disrupted.
Jun 4, 2021 — Contracts Bulletin
Jan 9, 2022 - This bulletin will discuss the basics for effectively implementing and incorporating changes into agreements, and will address how standard contracts, such as the American Institute of Architects.
Jan 9, 2022 - President Biden signed Executive Order 14042, “Ensuring Adequate COVID Safety Protocols for Federal Contractors.”
Jun 4, 2021 - The contract between my client and its customer set a specific production schedule, and had incentives and penalties if certain deadlines were not met. My client’s customer was demanding completion on schedule, and threatening to enforce penalties.