Contracts Bulletin: COVID-19 Contract Addenda - Considerations for the Subcontractor

Subcontractors, whether they hope to present their own COVID-19 addendum or have recently had a COVID-19 addendum included by general contractor or owner, should consider the following information before signing on the dotted line:Increased Cost and Time.

Subcontractors, whether they hope to present their own COVID-19 addendum or have recently had a COVID-19 addendum included by a general contractor or owner, should consider the following information before signing on the dotted line:

  • Increased Cost and Time. How a COVID-19 addendum addresses increased costs and time for performance under the original construction contract is likely the most important aspect of the addendum.
  • Safety Protocols. A COVID-19 addendum should address safety measures that will be taken at the jobsite
  • Liability. A COVID-19 addendum presents an opportunity for an owner or general contractor to shift COVID-19 liability to the subcontractor.
  • Sample Addendum to Construction Agreement.

Practically every construction project a contractor or subcontractor has been involved in over the past several months has been affected by COVID-19. As a result, COVID-19 contract addenda have become increasingly popular. While a potential trap for the unwary subcontractor, a COVID-19 addendum can also provide an opportunity to recover time, costs, and money.

Contracts Bulletin No. 5.5 was prepared by SMACNA’s general counsel. All members are encouraged to read this latest update.


Jun 17, 2020 Contracts Bulletin

Latest Articles


Contracts Bulletin #98: Change Orders and Extra Work: Tools for Change

Jan 9, 2022 - This bulletin will discuss the basics for effectively implementing and incorporating changes into agreements, and will address how standard contracts, such as the American Institute of Architects.


Contracts Bulletin #125: COVID-19 Vaccine Mandate for Federal Contractors

Jan 9, 2022 - President Biden signed Executive Order 14042, “Ensuring Adequate COVID Safety Protocols for Federal Contractors.”


Contracts Bulletin #65 (2.0): Force Majeure – A Clause for Our Times

Jun 4, 2021 - The contract between my client and its customer set a specific production schedule, and had incentives and penalties if certain deadlines were not met. My client’s customer was demanding completion on schedule, and threatening to enforce penalties.